MARKET PRICES
73300
1,471.50
405.50
2,350.00
7.75
· charting and more...
Prices delayed 30 min.
Rhodium updated daily.
REGISTER TO RECEIVE E-MAIL ALERTS
more...

Site last updated:
08 February 2010





Site designed by:
Motiv 
created by:
Ince New Media
 
OPERATIONS
OVERVIEW AND LOCATIONS
  
 

MINING OPERATIONS

PRODUCTION

Production of equivalent refined platinum production (metal in concentrate less assumed smelting and refining losses) from mining operations owned by Anglo Platinum, its attributable share of joint-venture mines and purchase of concentrate agreements, was 2.465 million ounces for the year, compared with 2.471 million ounces in 2007. Factors contributing to the marginal decrease include:
  • the disruption of operations at Amandelbult Mine, caused by a major flood; 
  • the suspension of operations to rehabilitate shaft steelwork at the Turffontein shaft of the Rustenburg Mine during the first half of the year;
  • an overall expected reduction in built-up head grade; 
  • severe electricity supply constraints in January and the associated ramp-up period when supply resumed; and 
  • safety- and labour-related stoppages.
Lower production volumes were recorded at Rustenburg, Amandelbult, BRPM, Mototolo, Lebowa and Western Limb Tailings Retreatment. 

The reductions resulting from production disruptions were offset by the increase in purchased ounces from Xstrata South Africa’s new Eland Platinum Mine, which began delivery to Anglo Platinum in December 2007, and by increased production from Mogalakwena, Union, Modikwa, Twickenham, Marikana and Kroondal.

The aggregate immediately available ore reserves for managed operations increased by 13%, to 16.1 months at 31 December 2008, as a result of the continued focus on equipping and redevelopment activities.

Mining operations are taking place at the Pandora Joint Venture, in which Anglo Platinum has a 42.5% stake, where an ore sale agreement is in place with Western Platinum Limited.

Pandora delivered 905,444 tonnes of ore during 2008, which yielded some 76,439 equivalent refined platinum ounces, in line with the 76,622 ounces in 2007. This production is excluded from Anglo Platinum’s reported production.
 

COSTS

Total cash on-mine costs for mining and retreatment operations increased by 26%, or R4.1 billion to R20.2 billion in the year, owing to substantial above-inflation pressures experienced in labour and contractor rates as well as key commodity input costs, including steel, fuel, chemicals, explosives, support and grinding media. As a result, the cash on-mine cost per equivalent refined platinum ounce (in respect of Anglo Platinum’s own mines plus its share of joint ventures) increased by 37% to R9,892 per ounce in 2008. The cost per tonne milled rose by 22% to R475. 

Total capital expenditure on the Anglo Platinum mining and concentrator operations and on its share of the joint-venture mines in 2008 was R10.1 billion, up 9% from R9.3 billion in 2007.
 

OUTLOOK

The key focus areas in 2009 for mining operations include: the achievement of the Group target of 2.4 million refined ounces with revised capital funding; the reduction in costs through asset optimisation initiatives; the reduction in contractor employees, in line with revised production levels; and actively managing the prices of key commodity input costs and the improvement of efficiencies from own enrolled employees.

Structures at Rustenburg Mine and Amandelbult Mine are under review. The mines will be restructured into smaller units to allow for more focused management. Marginal mines will be subject to continual reviews, and appropriate action will be taken to mitigate costs and increase cash generation. 
 

MECHANISATION AND NEW MINING TECHNOLOGIES 

The focus on mechanisation and new mining technologies includes the modernisation of ancillary mining functions and the appropriate mechanisation of conventional methods in stoping activities and elsewhere. 
 

Modernisation

Several technologies are being rolled out at the mines, to modernise conventional mining and thereby improve safety and productivity. These include the following:
  • Hydro-powered drill rigs for flat and inclined development and man-free box holing. 
  • The electro-hydraulic man-free box holing is being rolled out together with hand-held electric rock drills at selected sites. 
  • Ongoing modifications are being made to develop a more powerful electric rock drill to apply effectively in development ends where longer rounds are drilled. 
  • Trials continued with the radio remote controlled hydraulic scraper winch, with further modifications under way to improve communication linkage. 
  • A centralised blasting system has been successfully commissioned at a pilot site at Union’s Spud shaft. The rollout of the same system has started at Rustenburg Mine.
The focus for 2009 is to optimise performance through the rollout of applied new technologies to the conventional mining environment. 
 

Mechanisation

Underground trials began at Amandelbult Mine, with an extra low-profile equipment suite that was developed specifically for the semi-steep dipping mine. Encouraging progress has been made to date. Extra low-profile (down to a 1.2 metre stope width) and ultra low-profile mechanised mining present the most significant opportunities for full mechanised mining of  narrow tabular ore deposits. Continual efforts are made to develop appropriate technology that can address safety, productivity and the cost of full trackless mechanised mining at steeper dips and stope widths (down to 90 centimetres).

Further progress has been made with continuous mining methods, including rock cutting. Trials using the activated drum system continued during 2008 and trials and modifications will continue during 2009. The reef mole (RM900) is undergoing design changes, with underground trials planned for 2009. The oscillating disc cutter, which is a PlatTech collaborative research project, was trialled on a test block on surface with modifications, and underground trials are scheduled to start during 2009.
 

Mechanised skills development

Appropriate skills development is recognised as a key success factor in the effective rollout of trackless mechanised mining. Progress has been made with the development of the necessary mechanised training centres at both Twickenham and Waterval mines which will cater for the Eastern Limb and the Western Limb respectively. 


Print page

E-mail page
 
RELATED PAGES: